FERC Reissues Authorization for Cove Point LNG Terminal Expansion in Wake of D.C. Circuit Decision

Following a decision in July by the U.S. Court of Appeals for the District of Columbia Circuit vacating the orders authorizing the Cove Point Expansion Project, FERC reissued its authorization for the construction and operation of the LNG terminal expans
October 6, 2008

Following a decision in July by the U.S. Court of Appeals for the District of Columbia Circuit vacating the orders authorizing the Cove Point Expansion Project, FERC reissued its authorization for the construction and operation of the LNG terminal expansion this morning. The Commission’s order, available in the FERC eLibrary under Docket No. CP05-130, found that construction and operation of the Cove Point Expansion is in the public interest and can continue without causing unsafe leakage on Washington Gas Light’s (WGL) distribution system. The order on remand conditions the authorizations on limiting deliveries of imported LNG from the Cove Point Pipeline into Columbia Gas Transmission’s interstate pipelines to existing delivery volumes. The Commission found this would protect WGL from receiving additional volumes of regasified LNG.

Our Story

Sutherland Asbill & Brennan LLP is an international law firm helping the Fortune 100, industry leaders, sector innovators and business entrepreneurs solve their biggest challenges and reach their business goals. Dedicated to unfaltering excellence in client service, we are known for our business savvy and industry intelligence, providing creative and custom solutions for each of our clients. Industry and business experience makes the difference for our clients.

click to watch Videocast: DOL Fiduciary Rule Litigation Impacts
Videocast: DOL Fiduciary Rule Litigation Impacts
Atlanta, GA
Washington, DC
© 2016 Sutherland Asbill & Brennan LLP / Sutherland (Europe) LLP
MYBRIEFCASE
Add this page to MYBRIEFCASE
Add Page to MYBRIEFCASE
News/Commentary - FERC Reissues Authorization for Cove Point LNG Terminal Expansion in Wake of D.C. Circuit Decision
Current MYBRIEFCASE Pages
Save ChangesDownload MYBRIEFCASEClear All